16-03512N


  • Pinellas
  • Share


ADVERTISEMENT FOR BIDS
The School Board of Pinellas County, Florida will receive sealed Request for Qualifications in the Purchasing Department of the School Board of Pinellas County, Florida 301 - Fourth Street S.W., Largo, Florida 33770-3536 until 4 p.m. local time, on May 23, 2016 for the purpose of selecting a firm for Design Services required for the scope listed below.
Request for Qualifications: Architectural Design Services
RFQ# 16-906-212
Construct Public Use Swimming Pool
Tarpon Springs High School
1411 Gulf Road
Tarpon Springs, FL 34689

SCOPE OF PROJECT: The Pinellas County School Board (the district) requests qualification statements from experienced and qualified firms or individuals to provide Architectural Design Services to construct public use swimming pool.

Scope of work: The swimming pool will be 8 lanes with a diving well for competitive diving. There will be showering and changing facilities for men and women. We will have a building for storage and a separate building for the pump room and associated equipment. There should be office space and a concession stand, along with a ticket window for monitoring attendance.
Site improvement will include, but not limited to, the relocation of the existing retention pond.

Required RFQ documents can be downloaded from: www.publicpurchase.com

You must be registered in Public Purchase to access the RFQ documents.

TYPE OF DISCIPLINE REQUIRED: Architect.

LIST OTHER DISCIPLINES REQUIRED TO COMPLETE PROJECT:
Other disciplines required to complete this project are listed below. Please indicate the firm or firms you will be utilizing for this project and include their information on related forms. If you provide this discipline in house, please indicate as such.

• Civil Engineer • Landscape Architect
• Structural Engineer • Mechanical Engineer
• Electrical Engineer • Paint and Coating Consultant
• Pool Consultant

THE ESTIMATED CONSTRUCTION BUDGET: $1,500,000.00
TIMELINES FOR DESIGN DOCUMENTS SHALL BE AS FOLLOWS:
PHASE 1 SCHEMATIC DESIGN: 30 DAYS
PHASE 2 PRELIMINARY DESIGN DOCUMENTS & SPECIFICATIONS: 45 DAYS
PHASE 3 CONSTRUCTION DOCUMENTS & SPECIFICATIONS: 45 DAYS
Such time limitations shall be exclusive of review and approval.

BY ORDER OF THE SCHOOL BOARD OF PINELLAS COUNTY, FLORIDA

DR. MICHAEL GREGO, SUPERINTENDENT PEGGY O'SHEA
SUPERINTENDENT OF SCHOOLS CHAIRMAN
AND EX-OFFICIO SECRETARY LINDA BALCOMBE
TO THE SCHOOL BOARD DIRECTOR, PURCHASING
April 29; May 6, 13, 2016 16-03512N

View the PDF of the publication this ad appeared in

Sponsored Content